Re: Transferring from Renewables Obligation to FITs. I'm Confused....
by Ted Marynicz
at 2010-03-28 13:13:11
(Forum::Public::General)
Peter,
if you are a pre-July 2009 installation and are already registered for ROCs then there is nothing you immediately have to do with OFGEM.
Your current supplier should send you papers to complete to facilitate the ROC to FIT switch-over. I got mine from SSE yesterday - but the 31st March deadline doesn't apply to this.
ted