Re: Transferring from Renewables Obligation to FITs. I'm Confused....
by Ted Marynicz at 2010-03-28 13:13:11 (Forum::Public::General)
Peter,

if you are a pre-July 2009 installation and are already registered for ROCs then there is nothing you immediately have to do with OFGEM.

Your current supplier should send you papers to complete to facilitate the ROC to FIT switch-over. I got mine from SSE yesterday - but the 31st March deadline doesn't apply to this.

ted

Mail this to a friend
Transferring from Renewables O... Peter Henderson - 27/03
    Re: Transferring from Renewabl... Ted Marynicz - 28/03
       Re: Transferring from Renewabl... Roger Vincent - 29/03
       Re: Transferring from Renewabl... Peter Henderson - 1/04
If you'd like to post comments on this site, just register here

Powered by Novacaster