Proven 6KW output
by Simon Ridout at 2007-11-01 07:58:39 (Blog::SimonRidout)
The actual output of a wind turbine is of interest to many. I have therefore decided to 'publish' the output of my Proven 6kw turbine each month. Full details of the location can be found by searching for the Lake District National Parkl Planning Application 7/2006/4107. Wind speeds are about 10% less than those recorded for the nearest Met Office observation site, at St Bees Head. While installed on 30 May 2007, teething problems meant that the turbine was not performing properly until the start of October, indeed October's output equals that in the 4 months before!
Turbine Output October 2007
Total: 331 KWH
Daily output:
Max: 84KWH
Min: 0KWH
0-4 KWH 14 days
5-9 KWH 9 days
10-19 KWH 4 days
20+ KWH 4 days
--
Simonridout

Mail this to a friend
Proven 6KW output Simon Ridout - 1/11
    Re: Proven 6KW output Stuart - 1/11
       Re: Proven 6KW output Simon - 1/11
       Re: Proven 6KW output Simon Ridout - 1/11
          Re: Proven 6KW output muymalestado - 2/11
          Re: Proven 6KW output Simon - 2/11
             Re: Proven 6KW output Stuart - 2/11
                Re: Proven 6KW output Colin - 9/11
    Re: Proven 6KW output Simon Ridout - 1/12
       Re: Proven 6KW output Peter Benning - 18/12
    Re: Proven 6KW output Simon Ridout - 1/03